Location: Duncan, BC Services: LEED Commissioning, Integrated Systems Testing (IST), Electrical and IMIT Commissioning Project Value: Over $1.5 billion
Cowichan District Hospital represents ITSL’s largest project to date. Our scope includes LEED Commissioning, Integrated Systems Testing, Electrical Commissioning and Information Management/Information Technology (IMIT) Commissioning.
ITSL has completed extensive prefunctional inspections and functional performance testing across multiple building systems.
To support the scale and complexity of the project, ITSL introduced a dedicated Commissioning Manager position, with a senior commissioning professional stationed on-site full-time throughout the testing period. This position provides direct coordination between contractors, consultants and commissioning personnel, helping manage testing readiness, outstanding deficiencies and commissioning milestones.
Project Experience & Lessons Learned
Early Commissioning Planning: The Commissioning Provider’s plan must be incorporated into the overall construction schedule early, including individual system activation plans and key commissioning milestones. When milestones are missed, prompt corrective action is essential, as specialized commissioning personnel cannot always be mobilized on short notice.
Coordinated System Completion: Construction should be sequenced to deliver complete, operational systems and associated building areas. Completing architectural finishes while mechanical rooms remain unfinished, or completing mechanical rooms while the systems they serve remain under construction, creates significant challenges for functional testing. Coordinating the completion of entire systems allows testing to proceed more efficiently and minimizes repeated site visits.
Independent Prefunctional Verification: Although contractors perform their own quality assurance and quality control, our independent prefunctional inspections identified numerous deficiencies requiring correction before functional testing. This experience reinforces the importance of having technically experienced third-party commissioning personnel physically inspect equipment and installations rather than relying solely on contractor documentation.