What Is Testing & Balancing
Building Performance Starts with Proper Balance
Techical Definition
Testing, Adjusting, and Balancing (TAB) is the systematic process of verifying, adjusting, and documenting the performance of HVAC air and hydronic systems so they operate in accordance with the design intent. This includes airflow, water flow, temperature, pressure relationships, and, where applicable, sound levels throughout the building.
Mechanical systems can be installed exactly as shown on the drawings and still not perform correctly. Air may not reach spaces in the required quantities. Water flow may not be distributed properly through coils and terminal units. Rooms may be too hot, too cold, too noisy, under-ventilated, or incorrectly pressurized. TAB is the process that identifies those issues, corrects them where possible, and confirms how the system is actually performing.
TAB covers more than balancing air alone. Effective TAB evaluates the overall delivery and distribution of heating, cooling, and ventilation throughout a building. It confirms that fans, pumps, coils, terminal units, control devices, and distribution systems are working together to support comfort, indoor air quality, energy performance, and system operation.
Without independent TAB, buildings often experience uneven temperatures, poor ventilation, unstable pressurization, excessive noise, wasted energy, and systems that do not operate as intended. In healthcare and other critical environments, incorrect room pressurization or improper airflow can directly affect safety and operational requirements.
ITSL provides independent TAB, meaning our technicians are not affiliated with the mechanical contractor that installed the systems being tested. That independence supports objective findings, reliable adjustments, and unbiased reporting. Our TAB reports are relied upon by engineers, owners, healthcare authorities, and LEED project teams across BC.
TAB and commissioning are closely related, but they are not the same. TAB focuses on measuring, adjusting, and documenting HVAC system performance. Commissioning is the broader verification process that evaluates whether building systems as a whole are installed, operating, and integrated properly. Because ITSL performs both, we provide better coordination, clearer accountability, and a more complete understanding of how the building is actually performing.
Our Approach
Documented at Every Step
Initial system readings recorded before any adjustments are made. Final balanced condition captured in full. Dampers marked in their final position, so the work stays traceable long after we leave site.
Truly Independent
Our technicians aren’t affiliated with the mechanical contractor who installed the systems being tested. What we report is what we found.
One Firm, Two Disciplines
Because ITSL performs both TAB and commissioning, you get one team coordinating the full picture instead of two vendors pointing at each other when something doesn’t add up.
Since 1986
Decades of BC Interior HVAC experience, from routine commercial buildings to full hospital tower commissioning.
TAB Services
What ITSL Tests, Adjusts, and Documents
Our TAB scope is adapted to each system type and project from straightforward commercial HVAC to complex healthcare pressurization.
Air Distribution TAB
Systematic measurement and adjustment of supply, return, and exhaust airflows at every terminal device. Fan performance verification. Static pressure traverses at duct cross-sections. VAV box calibration and flow verification. Outside air measurement and adjustment.
Supply / Return / Exhaust
Fan Performance
VAV Calibration
Hydronic System TAB
Chilled water, heating water, and condenser water flow balancing at all terminal units: coils, fan coils, heat exchangers, and radiant panels. Pump curve verification. Control valve authority testing. System delta-T optimization for energy efficiency.
Chilled Water
Heating Water
Ultrasonic flow readings
Sound testing
Air change testing
Pump Performance
Healthcare Pressurization
Room-by-room pressure differential measurement and airflow direction verification for isolation rooms, operating rooms, clean rooms, and negative-pressure spaces. CSA Z317.2 compliance documentation. AII and PE environment verification.
CSA Z317.2
Isolation Rooms
Pressure Differentials
Sound & Vibration Testing
HVAC noise level measurement at occupied spaces against NC/RC design criteria. Equipment vibration measurement for fans, pumps, and AHUs. Duct-borne sound testing. Results compared against ASHRAE acoustic guidelines and project specifications.
NC / RC Curves
Fan Vibration
ASHRAE Acoustics
Existing Building Re-Balancing
ITSL provides rebalancing services for existing HVAC systems following renovations, tenant improvements, occupancy changes, and operational drift. Our team reviews how air and water are being delivered through the building, identifies issues caused by duct modifications, diffuser changes, control adjustments, or BAS-related performance problems, and recommends practical corrections to restore comfort, ventilation, pressurization, and energy performance.
Duct cleaning
Ultrasonic flow readings
Post-Renovation
Tenant Improvement
BC Hydro COP
Certified TAB Report
A complete TAB report is provided at project closeout, documenting design values, measured values, and percentage variance for each tested point. Reports are reviewed and signed by ITSL’s senior TAB technicians and formatted to support engineer review, LEED documentation, healthcare project requirements, and building permit closeout.
LEED Submission Ready
Engineer Sign-Off
Health Authority Accepted
TAB Services
Existing Building Re-Balancing
ITSL recommends a TAB survey as part of every recommissioning project, at the beginning of the Investigation Phase. We treat this as a functional test of the distribution systems. Before making recommendations, we confirm how air and water are actually moving through the systems. This helps identify low-cost issues, separate balancing problems from control or equipment problems, and provide real field data before capital upgrades are considered.
As a BC Hydro Continuous Optimization Program approved service provider, ITSL can also support eligible existing building investigations where rebalancing may be identified as a low-cost energy conservation measure.
8–13%
Energy savings reported from system balancing alone
30%+
Average savings when balancing is paired with diagnostics and repairs (National Comfort Institute)

TAB Services
HVAC System Surveys and Performance Audits
As buildings age, HVAC systems often drift from their original design intent. Renovations, equipment replacements, control changes, damper adjustments, sensor drift, valve issues, and undocumented modifications can all affect how a building operates. A focused HVAC system survey is a practical way to understand current system condition before larger comfort, energy, or maintenance issues develop.
Inland Technical Services provides field-based HVAC system surveys and performance audits for existing buildings across BC and Western Canada. Our team measures actual system performance, reviews equipment operation, and checks airflow and hydronic flow. We evaluate outside air and exhaust quantities and identify issues that may be affecting comfort, ventilation, reliability, or energy use.
These surveys are especially valuable before design upgrades, equipment replacements, recommissioning work, major control changes, or facility planning. Before a system can be improved, the owner and consultant team need reliable field data showing how the system operates today. Inland Technical provides that information through measured results, practical troubleshooting, and clear documentation.
Our reviews can include air and water balancing checks, fan and pump performance, electrical measurements, temperature and pressure readings, control response, critical environment pressure relationships, equipment condition, and existing system mapping. The scope can be tailored to a full building review or focused on specific systems, problem areas, or operational concerns identified by the facility team.
Where existing documentation no longer reflects the building, Inland Technical can map HVAC systems in the field and prepare professional AutoCAD and PDF drawings showing the actual on-site layout. These drawings can be labelled and colour-coordinated to help building managers, operators, consultants, and maintenance staff understand the system, troubleshoot issues, plan maintenance, and support future renovations.
Existing building reviews also provide a strong starting point for energy efficiency improvements. Incorrect airflow, excessive outside air, poor scheduling, simultaneous heating and cooling, failed valves or dampers, undocumented system changes, and inefficient fan or pump operation can all increase operating costs. By combining TAB experience, commissioning review, controls verification, field measurements, and accurate system documentation, Inland Technical helps owners identify practical improvements that support comfort, reliability, maintainability, and reduced energy use.
TAB Services
Fume Hood Testing
Inland Technical Services provides testing and certification of chemical fume hoods for laboratories, healthcare facilities, educational buildings, and other controlled environments. Fume hoods are critical safety devices, and their performance needs to be confirmed through proper field testing, measurement, and documentation.
Our fume hood testing services are completed in accordance with applicable CSA, WorkSafeBC, project specification, and industry testing requirements. Testing can be completed as part of new construction commissioning, routine certification, recommissioning, troubleshooting, or facility maintenance programs.
Typical fume hood testing includes:
Face velocity profiling
Airflow smoke visualization
Cross draft airflow testing
Airflow alarm verification
Sash position and operating condition review
VAV fume hood response testing, where applicable
Documentation of measured results and deficiencies
Where specified, Inland Technical can also support ASHRAE 110 testing, including face velocity testing, smoke visualization, cross draft review, and containment performance evaluation.
Our approach is field based and practical. We verify how the hood is actually operating under site conditions, identify issues that may affect containment or user safety, and provide clear documentation for owners, consultants, and facility teams.
TAB Services
Testing and Balancing After Duct Cleaning
Duct cleaning can improve air system cleanliness, but it can also change how the system performs. Removing buildup from ductwork, grilles, diffusers, coils, dampers, and terminal units can affect airflow, static pressure, and system balance. Cleaning work may also disturb balancing dampers, access panels, sensors, or diffuser settings.
For this reason, testing, adjusting and balancing should be completed after duct cleaning whenever system performance matters. A post cleaning TAB review confirms that each area is receiving the correct airflow, outside air quantities remain appropriate, exhaust systems are operating as intended, and the HVAC system still matches the design or operational requirements.
Inland Technical Services provides field based airflow testing and balancing following duct cleaning work. Our team measures actual performance at the equipment and air terminals, identifies changes caused by the cleaning process, and documents any deficiencies that require correction.
This helps owners confirm that duct cleaning has not only improved cleanliness, but also maintained or improved comfort, ventilation, pressure relationships, and overall HVAC system performance.
TAB Services
Fire Damper Drop Testing
Fire damper drop testing confirms that fire dampers, smoke dampers, combination smoke and fire dampers, and fire stop flaps are accessible, documented, and able to operate as intended. These devices are critical life safety components and should not be treated as a visual inspection only.
Inland Technical Services provides fire damper drop testing for new construction, renovation projects, and existing buildings. Our team physically tests damper operation, reviews access for inspection and maintenance, verifies damper locations, documents deficiencies, and supports retesting after corrective work is complete.
For new construction and renovation projects, drop testing is most effective before ceilings are closed, occupancy is granted, or final turnover is reached. Testing at this stage allows inaccessible dampers, missing access panels, installation issues, obstructions, damaged components, or labelling problems to be corrected while trades are still active on site.
For existing buildings, fire damper drop testing should be included as part of the ongoing fire safety maintenance program. In BC, the Fire Code requires fire dampers, smoke dampers, combination smoke and fire dampers, and fire stop flaps to be inspected at intervals not greater than 12 months and tested in accordance with NFPA 80.
NFPA guidance also identifies longer term testing intervals after initial acceptance. Fire and smoke dampers are generally inspected and tested one year after initial acceptance and then every 4 years, except in hospitals, where the interval is every 6 years. Additional testing may also be required after repairs, renovations, access changes, or system modifications that could affect damper operation.
Our fire damper drop testing services can include physical drop testing, accessibility review, location verification, deficiency documentation, corrective action tracking, retesting, signed reporting, and as built drawing support where required.
Healthcare Specialization
TAB for BC’s Most Demanding HVAC Environments.
Healthcare HVAC systems are categorically different from commercial HVAC. Airborne infection control, clean room standards, sterile processing ventilation, medical gas supply air, and pharmacy pressurization all require TAB results that can be directly linked to patient safety outcomes.
ITSL has performed TAB on numerous hospital towers and counting and dozens of recent phased healthcare renovations across BC, including operating suites, intensive care units, neonatal units, sterile processing departments, and pharmacy clean rooms, all environments where pressurization and airflow direction are regulated by CSA Z317.2 and other infection control standards.
Our TAB technicians understand the clinical context of the spaces they’re testing. An incorrectly pressurized isolation room isn’t a construction deficiency to be noted in a report, it’s a patient safety issue to be corrected before occupancy. That understanding shapes how we approach our projects.
Healthcare TAB Standards
CSA Z317.2: Healthcare HVAC
CSA Z8001: Healthcare Cx
ASHRAE 170
BC Health Authority Standards
Infection Control Protocols
PHSA Requirements
Healthcare TAB: Selected Projects
Royal Inland Hospital: Patient Care Tower
Full TAB scope for a new hospital tower in Kamloops. LEED Gold project. Coordinated with commissioning and IST scopes under a single ITSL contract.
Kelowna General Hospital, Multiple Phases
TAB across cardiac, operating room, MRI, and catheterization lab renovations. Work included phased access coordination with clinical teams in an occupied hospital environment.
Kelowna General Hospital Ambulatory Care Centre / Centennial Building
Full TAB services for the LEED Gold Ambulatory Care Centre at Kelowna General Hospital, including major clinical, surgical, diagnostic, renal, emergency, and support spaces.
Penticton Regional Hospital, Multiple Phases
TAB and pressurization verification for various phases of hospital work.
Haida Gwaii Hospital
TAB services for healthcare facility work in Haida Gwaii, supporting ITSL’s experience with remote and regional healthcare projects.
Trail Memorial Hospital, Multiple Phases
TAB services for multiple phases of hospital work in Trail, supporting continued healthcare system upgrades in the Kootenays.
Comox Valley and Campbell River Hospitals
Full TAB for LEED certified hospital facilities on Vancouver Island, demonstrating ITSL’s province wide healthcare TAB capability.
Whitehorse General Hospital Expansion
TAB services for a hospital expansion in Whitehorse, YT, extending ITSL’s healthcare expertise beyond BC into northern Canada.
TAB vs. Commissioning
Two Distinct Scopes, Better Together
TAB and commissioning are related, but they’re not the same. Knowing the difference helps owners, engineers, and project teams plan the right scope at the right stage.
Testing and Balancing
Adjusts and documents system flows
What it does
Measures, adjusts, and documents airflow, water flow, pressure relationships, temperatures, and final balanced conditions.
When it happens
Once mechanical systems are installed, operational, and ready for testing. Larger projects may phase it as systems come online.
Who requires it
Project specifications, engineers of record, owners, healthcare authorities, LEED project teams, and commissioning providers.
Commissioning
Verifies systems perform as intended
What it does
Confirms building systems are installed, operating, and integrated in accordance with the Owner’s Project Requirements and design intent. TAB is one key input.
When it happens
Ideally starts at design and runs through construction, handover, and post-occupancy.
Who requires it
LEED projects, healthcare and institutional facilities, owner-driven quality programs, and complex buildings with integrated mechanical, electrical, controls, and life safety systems.
Better Coordination When ITSL Performs Both
When ITSL performs both TAB and commissioning, field data, issue tracking, and system verification are connected. TAB findings can be reviewed directly against commissioning requirements, deficiencies can be tracked through shared issue logs, and the project team receives clearer reporting on what was tested, what was adjusted, and what still requires resolution.
Addressing Perceived Conflict of Interest
A perceived concern can arise when one firm provides both TAB and commissioning. In practice, having the owner, design consultants, and project team review TAB results, test procedures, issue logs, and final documentation reduces that concern.
The greater conflict is usually when a party is asked to verify its own work, such as a design consultant commissioning systems they designed or an installing contractor verifying systems they installed. ITSL does not design or install the systems being verified. Our role is to measure performance, document findings, identify issues, and support resolution.
TAB Projects
Testing & Balancing Across Interior BC and Beyond
A selection of projects where ITSL has delivered certified TAB services across healthcare, education, civic, and commercial sectors.
Healthcare · Kamloops
Royal Inland Hospital Patient Care Tower
Full air and hydronic TAB for the new acute care tower. Pressurization verification for isolation rooms, ORs, and sterile processing. Coordinated with commissioning and IST scopes under single ITSL engagement.
Kamloops, BC
LEED Gold 2023
Healthcare
Education · LEED Gold
UBCO Health Sciences Building
Air and hydronic TAB for LEED Gold laboratory and academic building at UBC Okanagan. Complex fume hood exhaust balancing, pressurization hierarchy between laboratory and support spaces, and BAS setpoint verification.
Kelowna, BC
LEED Gold
Lab HVAC
Civic · Kamloops
Thompson Rivers University: Multiple Buildings
TAB across multiple TRU campus buildings including the Library and Old Main Retrofit. Phased delivery alongside active academic operations requiring careful scheduling to avoid disruption to university functions.
Kamloops, BC
New & Existing
Occupied Campus
Healthcare · Kelowna
Kelowna General Hospital: Phased Renovations
Ongoing TAB relationship across cardiac, OR, MRI, and cath lab renovations at KGH. Extensive experience managing TAB access in a live hospital environment with strict infection control and operational requirements.
Kelowna, BC
Multi-phase
Occupied Facility
Commercial · Okanagan
Mission Hill & Burrowing Owl Wineries
TAB for specialized winery HVAC systems including barrel storage temperature control, production facility ventilation, and hospitality space conditioning. Temperature and humidity precision is critical to wine production quality.
Okanagan, BC
Commercial
Specialized HVAC
Residential · BC Housing
BC Housing Projects: Interior BC
TAB for BC Housing social housing developments across Quesnel, Prince George, Nelson, Cranbrook, Fernie, and Powell River. LEED-certified buildings requiring certified TAB reports for both building permit closeout and LEED submission.
Interior BC
LEED Certified
BC Housing
Why Inland Technical
What Sets ITSL’s TAB Work Apart
Local Presence Across the BC Interior
With offices in Kamloops and Kelowna, ITSL is positioned to support projects throughout the BC Interior and across BC. Our technicians are familiar with regional project delivery, local contractors, and the buildings we work in, which helps support consistent site presence, practical coordination, and efficient issue resolution.
Healthcare TAB Experience
Healthcare TAB requires more than standard airflow measurement. It involves careful attention to room pressurization, ventilation rates, infection control requirements, phased access, and occupied building conditions. ITSL has delivered TAB services on hospital towers, clinical renovations, operating rooms, diagnostic imaging areas, catheterization labs, and other critical healthcare environments throughout BC and beyond.
Detailed Balancing Planning
Before final TAB begins, ITSL develops a detailed balancing plan that outlines the expected duration of work, the sequence of systems that need to be started and tested, and any known roadblocks that could affect completion. This helps the project team understand what needs to be ready, where coordination is required, and how TAB can proceed without creating avoidable delays at closeout.
TAB Supported by Commissioning Experience
ITSL’s TAB work is supported by decades of commissioning experience. We understand how measured airflow, water flow, pressure relationships, and system operation affect the broader performance of a building. This allows our team to identify issues clearly, communicate them effectively, and provide reports that are useful to owners, engineers, contractors, and commissioning teams.
Clear, Traceable Field Reporting
Our TAB process documents how systems are found, adjusted, and left. Initial readings are recorded before adjustments are made, final readings are documented after balancing is complete, and dampers are marked in their final balanced position. This gives project teams clear, objective records of actual system performance and helps preserve the completed balance after turnover.
Real Time Issue Tracking
When issues are identified in the field, ITSL can track them in shareable issue tracking platforms with items assigned to the responsible parties. This helps owners, engineers, contractors, and commissioning teams see what was found, who is responsible, and what remains open, reducing missed items at closeout.
Decades of Regional Project Experience
ITSL has been serving the BC Interior since 1986. Over that time, we have worked alongside many of the region’s mechanical engineers, contractors, owners, healthcare authorities, institutions, and project teams. That experience helps us understand project expectations, coordinate effectively in the field, and deliver TAB reports that support closeout and long term building operation.
Integrated TAB and Commissioning Capability
TAB and commissioning are separate scopes, but they are closely connected. When ITSL is retained for both, TAB findings can be coordinated directly with the commissioning process, helping reduce handoff gaps and making it easier to track field issues through to resolution.
Existing Building Rebalancing and Energy Optimization
ITSL also supports existing building rebalancing and energy optimization investigations. As buildings age, are renovated, or operate differently than originally intended, system balance can drift. Rebalancing can often improve comfort, ventilation, pressurization, and energy performance without major capital upgrades.
Falcon Engineering has worked with Inland Technical Services on both tendered and design build projects with great success. ITS brings strong technical expertise with regards to the balancing and commissioning services required to bring a project to a successful conclusion.
Andrew Stringer, P.Eng, Principal, Falcon Engineering
Building Types We Balance
Hospitals
LEED
Heavy Industrial and Mining
Institutional such as University & College
K–12 Schools
Commercial
Civic & Aquatic
Multi-Unit Residential
BC Housing
Labs & Research
Wineries
Common Questions
Testing & Balancing: Answered
Our Offices
Two Locations.
We work where your buildings are.
Based in Kamloops and Kelowna we serve all of BC including Thompson-Okanagan, Kootenays, Peace Country, Cariboo, interior and beyond.